Following site clareance a crushed stone piling mat is laid across the building footprint to accommodate the piling rig, whilst elsewhere on the site, infrastructure works are progressed in connection with the water management systems

THE PILING RIG IS POSITIONED ON SITE

PILE CAGES AWAITING INSTALLATION

MILL POND DRAINED & REEDS CUT BACK

THE POND OVERFLOW SLUICE GATE IS REVEALED

THE NEW HEADWALL TO THE MILL RACE OUTFALL IS CAST AWAITING DELIVERY OF SPECIALLY SOURCED ENGINEERING BRICK FACINGS