MILL HOUSE - HANTS Following site clareance a crushed stone piling mat is laid across the building footprint to accommodate the piling rig, whilst elsewhere on the site, infrastructure works are progressed in connection with the water management systems ![]() THE PILING RIG IS POSITIONED ON SITE | ||
![]() PILE CAGES AWAITING INSTALLATION | ![]() MILL POND DRAINED & REEDS CUT BACK | ![]() THE POND OVERFLOW SLUICE GATE IS REVEALED |
![]() THE NEW HEADWALL TO THE MILL RACE OUTFALL IS CAST AWAITING DELIVERY OF SPECIALLY SOURCED ENGINEERING BRICK FACINGS |